Evonik – Antwerp site

NESS restores heat recovery in an existing system

NESS Wärmetechnik GmbH replaced a faulty air preheater at Evonik’s Antwerp site. The original unit had been installed in 2010 as part of a NESS project and was replaced with an identical W 3626 model.

The focus was on restoring heat recovery and carrying out the work within the existing system layout.

Initial Situation

A faulty component in a proven system design

The existing air preheater had failed and needed to be replaced. Its function was to use heat from the flue gases leaving the heater to preheat the combustion air. This heat recovery helps reduce fuel consumption, energy costs and CO₂ emissions.

The identical replacement unit was intended to restore this function within the existing system design.

What does the customer say about the project?

Jurgen Devleeschouwer | Plant engineer Engineering Evonik

„Our old Ness preheater had been in service since 2010 and showed severe internal corrosion. As a result, the heat exchange was no longer optimal and the burner parameters were out of specification, making a 1:1 replacement necessary. After defining the scope with Ness, we quickly established an action plan and rolled it out successfully. Thanks in part to strong communication between the project teams, we were able to complete the equipment replacement during a planned shutdown.

This kept downtime & costs to a minimum and allowed us to start up the new preheater without any issues. Overall, this was a very positive experience.“

Similar challenge at your location? We advise you personally and competently!

1) Our task

Removing and replacing the air preheater

NESS removed the faulty air preheater and installed the new unit at the Antwerp site. The scope of work included dismantling and reinstalling the connected air and flue gas ducts.

2) Technology in focus

Using flue gas heat to preheat combustion air

The new W 3626 air preheater has a heat transfer capacity of approximately 779 kW. It transfers heat from the hot flue gases to the combustion air, returning that energy to the process.

The identical replacement unit performs the same function as the original. The aim was to retain the existing heat recovery function.

3) Implementation

Working in line with site safety requirements

Scaffolding was required to access the relevant areas of the plant. The existing air and flue gas ducts had to be dismantled before the replacement and reconnected after the new air preheater was installed.

The work was carried out in accordance with the safety regulations in force at the Evonik site. The NESS project management team reported that collaboration with the customer went very well.

4) The result

Heat recovery restored

The project was completed on 25 June 2026. The new air preheater replaces the faulty component and allows heat from the flue gases to continue to be used to preheat the combustion air.

The project shows how replacing individual components can help keep existing industrial heating systems operational.

Do you have a specific enquiry? We look forward to hearing from you!

© Copyright NESS Wärmetechnik GmbH | Remsstrasse 24, 73630 Remshalden | Tel. +49 (7181) 96 75 -0 | Fax +49 (7181) 4 26 12 | info@ness.de | www.ness.de